Crusoe ayaa ka tagtay qorshaha $1.25 biloyon ee ay lahayd Boom Supersonic
Shirkadda AI-ka ee Crusoe, oo ku taalla magaalada Denver, ayaa xukuntay qorshihii ay lahayd shirkadda Boom Supersonic, iyadoo ku bixisay lacag dhan $1.25 biloyon oo ay ku iibinayso turbinada Superpower, balse qorshuhu wuxuu ku dhacay.
Crusoe iyo Boom Supersonic ayaa ka tagay iskaashiga
Crusoe, oo sanadkii 2018-kii ka billowday inay noqoto shirkad iibisa Bitcoin, ayaa hadda noqotay mid ka mid ah shirkadaha ugu weyn ee abuuraya xarumaha AI-ka, iyadoo ku jira Abilene, Texas, oo ay u abuurto OpenAI. Shirkaddu waxay ku guuleysatay inay hesho lacag dhan $3.9 biloyon, iyadoo haddana ka tagtay qorshihii ay lahayd Boom Supersonic.
Blake Scholl, oo ah hoggaamiyaha Boom Supersonic, wuxuu ku sheegay barta X-ka in iskaashiga u dhaxeeya labada shirkadood uu ka dhacay, isagoo sheegay in turbinada Superpower aysan ahayn qayb ka mid ah qorshaha ugu horreeya ee Crusoe. Wuxuu intaas ku daray inay diyaar u yihiin inay bixiyaan 250MW bishii soo socota, iyadoo ujeeddu tahay inay gaaraan 1GW sanadka 2028.
Qorshaha turbinada Superpower ee Boom Supersonic
Boom Supersonic waxay ku bilowday inay iibiso turbinada Superpower, oo ah nooc ka mid ah injineerka Symphony, kaas oo loo isticmaalo samaynta samafadaha hawada. Turbinadan waxay leeyihiin 80% oo ka mid ah qaybaha ku jira injineerka Symphony, iyadoo Crusoe ay horey u heshay inay noqoto macaamiisha ugu horreeya ee qorshahan.
Crusoe waxay horey u heshay inay bixiso $1.25 biloyon oo ay ku iibiso 29 turbin oo ka mid ah kuwa Superpower, iyadoo qorshuhu ahaa inay bilowdaan sanadka 2027. Hase yeeshee, qorshuhu wuxuu ku dhacay, iyadoo Crusoe ay sheegtay inay ka tagtay iskaashiga Boom Supersonic.
Saameynta qorshahan oo ka dhacay
Crusoe waxay sheegtay in xarunta Abilene, oo ay ku abuurto OpenAI iyo Oracle, ay u isticmaasho xawaaraha, halka xarunta cusub ee Microsoft, oo ah 900 megawatt, ay u isticmaasho turbinada hawada. Shirkaddu waxay sheegtay inay dooran karto noocyada kala duwan ee xawaaraha, iyadoo aanay u baahnayn turbinada Superpower.
Boom Supersonic waxay ku guuleysatay inay hesho lacag dhan $300 milyan, iyadoo ujeeddu tahay inay ka faa'iideysato qorshaha Superpower si ay uga faa'iideysato samafadaha hawada. Laakiin, inay ka tagto macaamiisha ugu horreeya, waa calaamad ah in qorshuhu uu ka dhacay.
Denver-based AI data center builder Crusoe has ended its partnership with Boom Supersonic, abandoning a $1.25 billion plan to power its facilities with the company's stationary turbines. The deal, which was set to begin deliveries in 2027, collapsed after Crusoe decided the turbines did not fit its near-term energy strategy at its Texas campus.
The Deal Falls Apart
Crusoe, which recently raised $3.9 billion, had agreed to purchase 29 of Boom's 42-megawatt Superpower turbines for a total of $1.25 billion. The first deliveries were scheduled to start in 2027, but the partnership has now been called off by Boom Supersonic CEO Blake Scholl.
Boom's Superpower turbine shares roughly 80% of its parts with the Symphony engine being developed for the Overture supersonic passenger jet. The company had raised $300 million last year specifically to commercialize the stationary power plant business, with profits intended to help fund Overture's development.
Why Crusoe Walked Away
Scholl explained on X that turbines are no longer part of Crusoe's near-term primary power mix at its Abilene campus, making a launch partnership unfeasible. Crusoe confirmed to TechCrunch that it is no longer doing business with Boom, citing the need to stay flexible with energy solutions as its portfolio grows.
Crusoe's initial 1.2 gigawatt data center in Abilene, built for Oracle and OpenAI, is currently powered by the grid, with a separate gas-turbine plant used only for backup. A new 900 megawatt facility for Microsoft will instead rely on on-site gas turbines, further reducing the need for Boom's turbines.
Boom's Next Steps
Despite losing its launch customer, Boom plans to deliver approximately 250 megawatts of Superpower turbines to other sites next year, with a target of 1 gigawatt by 2028. Scholl expressed gratitude for Crusoe's role in shaping the Superpower product and left the door open for future collaboration.
Crusoe's spokesperson Andrew Schmitt stated that the company remains open to turbines as one option among wind, solar, batteries, and the grid, but that the partnership was not the right fit at this time. The loss of its first customer is seen as a setback for Boom, which had counted on the deal to validate its new business line.
Ilaha iyo xuquuqda sawirka
Sawir: TechCrunch Xigasho